Notice of Claim Against a Government Entity
Most states require written notice to a state agency, city, county or school district before suit.
Find out where you stand — what state are you in?
DocDraft provides document preparation, not legal advice.
Introduction
A notice of claim tells a state agency, city, county or other public body about an injury or loss before you sue it. Most states require one, and a few make it optional or set no notice deadline. Deadlines run from 45 days to several years.
Key Things to Know
- 1
Where a state requires notice, the deadline is short and strict. Depending on the state and the entity, it can be as short as 45 days or run for several years, and missing it can bar the claim. Reading the statute or contacting the entity's clerk or risk management office confirms the current rule.
- 2
Check what starts the clock. Some states count from the date of the incident, others from when the claim accrued or when the injury was or should have been discovered.
- 3
Claims against the state itself and claims against a city, county or school district often follow different statutes, deadlines and recipients. Identify which kind of entity was responsible before you file.
- 4
The notice must reach the office the statute names, such as a city or county clerk, the attorney general, a claims board or a risk management office. Some states also set the delivery method, such as certified or registered mail or personal delivery.
- 5
Some governments publish an official government claim form, and some require it. Where a form is required, use it and follow its instructions.
- 6
Most notices describe the date, time and place of the incident, what happened, the entity or employee involved, and the injury or damage. Some states also require a specific dollar amount, an itemized statement or a sworn signature, and some bar stating an amount in certain claims.
- 7
In most states, filing the notice is a step before a lawsuit, not the lawsuit itself. Many states give the entity a set time to respond and set a separate deadline to sue after a denial. A few make it optional or set no separate notice deadline. Each state's page gives its own rule.
Notice of claim deadlines by state
The main notice rules for the 42 states and the District of Columbia listed below, and the statutes that set them. Where a state sets no separate notice deadline, the row shows its suit or waiting rule. Rules differ for claims against the state and against a city, county or other local body. Open your state's page for what starts the clock, who receives the notice and how to deliver it.
| State | Deadline | Statute |
|---|---|---|
| Alabama | City tort claims: 6 months (other claims 2 years); county: 12 months; State: 1 year (death: 2 years) | Ala. Code 11-47-23, 11-12-8, 41-9-65 |
| Arizona | State and local: 180 days after the cause of action accrues | A.R.S. 12-821.01 |
| California | State and local: 6 months (death, injury, personal property, crops); 1 year for others; late claim: apply to the entity | Gov. Code 911.2, 911.4 |
| Colorado | State and local: 182 days after discovery of the injury | C.R.S. 24-10-109 |
| Connecticut | State: 1 year after accrual (3-year outer limit); town and employee sued together: 6 months; town road defect: 90 days | Gen. Stat. 4-148, 7-465, 13a-149 |
| Florida | State and local: 3 years after accrual; wrongful death claim to DFS: 2 years | Fla. Stat. 768.28(6) |
| Georgia | State: 12 months after loss was or should have been discovered; city: 6 months from the event; county: generally 12 months | O.C.G.A. 50-21-26, 36-33-5, 36-11-1 |
| Hawaii | County notice: 2 years after accrual; State: suit within 2 years | HRS 46-72, 662-4 |
| Idaho | State and local: 180 days from when the claim arose or should have been discovered | Idaho Code 6-905, 6-906 |
| Illinois | State injury: 1 year (death: later of death or estate qualification), unless claim is filed in it; most local suits: 1 year | 705 ILCS 505/22-1; 745 ILCS 10/8-101(a) |
| Indiana | State: 270 days; city, county or other subdivision: 180 days; incapacity: 180 days after it ends | IC 34-13-3-6, 34-13-3-8, 34-13-3-9 |
| Iowa | State: written claim within 2 years after accrual; local: suit within 2 years | Iowa Code 669.13, 670.5 |
| Kansas | Local: notice before suit, within the 2-year injury or death limit; suit waits up to 120 days, then at least 90 days to sue | K.S.A. 12-105b(d) |
| Kentucky | State: 1 year after accrual; city bridge, street, sidewalk, alley or other public thoroughfare defect: 90 days | KRS 49.120, 411.110 |
| Maine | State and local: 365 days after accrual; later only for good cause, within the 2-year limit | 14 M.R.S. 8107, 8110 |
| Maryland | State and local: 1 year after the injury; a court may excuse a missed notice for good cause, unless it prejudiced the defense | SG 12-106; CJP 5-304 |
| Massachusetts | State and local: presentment within 2 years after the cause of action arose | G.L. c. 258, section 4 |
| Michigan | State: 6 months (injury, property) or 1 year; highway defect: 120 days (under 18: 180 days); sewage: 45 days after discovery | MCL 600.6431, 691.1404, 691.1419 |
| Minnesota | State and local: 180 days after discovery (wrongful death: 1 year) | Minn. Stat. 3.736, 466.05 |
| Mississippi | State and local: notice at least 90 days before suit; suit within 1 year | Miss. Code 11-46-11 |
| Missouri | Covered cities, street, sidewalk, bridge or thoroughfare defect: 90 days | RSMo 77.600, 79.480, 82.210 |
| Montana | No separate notice deadline; claim and suit within 3 years (injury) or 2 years (property); State: 120 days to decide | MCA 2-9-301, 2-9-302 |
| Nebraska | State: 2 years; city, county or other subdivision: 1 year | Neb. Rev. Stat. 81-8,227, 13-919 |
| New Hampshire | Local: 60 days from injury (discovery if not reasonably discoverable); State: 180 days; a late notice bars only on prejudice | RSA 507-B:7, 541-B:14 |
| New Jersey | State and local: 90 days after accrual; late notice only with court leave; suit waits 6 months | N.J.S.A. 59:8-8, 59:8-9 |
| New Mexico | State and local: 90 days after the occurrence; excused if the entity had actual notice | NMSA 41-4-16 |
| New York | Local and State tort: 90 days; State contract and other: 6 months; wrongful death (both): 90 days from estate appointment | GML 50-e; Court of Claims Act 10 |
| North Carolina | State: claim to the Industrial Commission within 3 years after accrual (wrongful death: 2 years after death) | G.S. 143-297, 143-299 |
| North Dakota | State: 180 days after discovery (serious injury: 1 year; waived for sexual-offense claims) | N.D.C.C. 32-12.2-04 |
| Oklahoma | State and local: 1 year after the loss (death: 1 year after the death) | 51 O.S. 156 |
| Oregon | State and local: 180 days after the loss (wrongful death: 1 year), excluding up to 90 days of incapacity | ORS 30.275 |
| Pennsylvania | State and local: 6 months after the injury or accrual; excused on a reasonable excuse | 42 Pa.C.S. 5522 |
| Rhode Island | Town highway, causeway or bridge defect: 60 days; other town claims: presentment, 40-day wait; State: suit in 3 years | R.I. Gen. Laws 45-15-9, 45-15-5, 9-1-25 |
| South Carolina | Optional; if filed, 1 year after the loss was or should have been discovered; suit within 2 years (3 if a claim was filed) | S.C. Code 15-78-80, 15-78-110 |
| South Dakota | State and local: 180 days after the injury; minors and incapacitated persons may get more time from a court | SDCL 3-21-2, 3-21-4 |
| Texas | 6 months after the incident; a city charter can set its own period; excused on actual notice | Tex. Civ. Prac. & Rem. Code 101.101 |
| Utah | State and local: 1 year after the claim arises, subject to a discovery rule | Utah Code 63G-7-401, 63G-7-402 |
| Virginia | State: 1 year; county, city or town negligence: 6 months; excused on actual knowledge | Va. Code 8.01-195.6, 15.2-209 |
| Washington | State and local: present the claim form before suit, within the limitation period; suit waits 60 days | RCW 4.92.110, 4.96.020 |
| District of Columbia | 6 months after the injury or damage (must be received) | D.C. Code 12-309 |
| West Virginia | State agency: notice at least 30 days before suit; local: suit within 2 years | W. Va. Code 55-17-3, 29-12A-6 |
| Wisconsin | Local and State employee: 120 days after the event; local negligent inspection: 1 year after discovery | Wis. Stat. 893.80, 893.82 |
| Wyoming | State and local: 2 years after the act, error or omission, or after discovery if not reasonably discoverable | W.S. 1-39-113 |
Key Decisions
The Government Entity
- Most Common Option
- Most Common Option
What Happened
- Most Common Option
- Most Common Option
Notice of Claim Requirements
File Before the Notice Deadline
Most states require notice before a claim against a government, and the deadlines are short and strict. They differ by state and by type of entity, and missing one can bar the claim.
Send It to the Office the Law Names
Each state names who receives the notice, such as a city or county clerk, the attorney general, a claims board or a risk management office. A notice sent to the wrong office may not count.
Describe When, Where and How It Happened
Give the date, time and exact place of the incident, explain what the entity or its employee did or failed to do, and name the department or employee involved where you know it.
Describe the Injury or Damage
Describe the injuries, the treatment received or the property damage, and attach supporting records such as bills, photos or repair estimates.
State an Amount Where Required or Allowed
Some states require a specific dollar amount or an itemized statement of damages, and a notice without one can be defective there. Others make the amount optional, and some bar it in certain claims, such as a California claim over $10,000.
Sign It, and Swear to It Where Required
Sign and date the notice, and have it sworn or verified where the statute or form requires it. Check the statute and any required form for the entity involved to see how it must be signed.
Use the Official Claim Form if There Is One
Some governments publish their own government claim form, and some require it. Where a form is required, use it and follow its instructions.
Deliver It by an Accepted Method and Keep Proof
Some statutes set the delivery method, such as certified or registered mail or personal delivery. Keep a copy of the notice and proof of the date it was delivered or received.
Wait for the Response Period Before Suing
Many states give the entity a set time to respond, after which the claim may be treated as denied. A separate deadline to sue may then apply.