Florida Notice of Claim Against Government

Written claim to the agency, plus DFS unless a city, county or the Florida Space Authority.

Find out where you stand in Florida

DocDraft provides document preparation, not legal advice.

Introduction

Fla. Stat. 768.28(6) requires a written claim within 3 years after it accrues, or within 2 years to DFS for wrongful death. Claims go to the agency, and also to DFS unless the claim is against a city, county or the Florida Space Authority.

Key Things to Know

  1. 1

    The deadline is strict. Under Fla. Stat. 768.28(6)(a), no suit may be brought unless the claim was presented in writing within 3 years after it accrues. Reading the statute or contacting the agency's risk management office confirms the current rule.

  2. 2

    Wrongful death claims are on a shorter clock: the written claim to the Department of Financial Services is due within 2 years after the claim accrues.

  3. 3

    One statute covers both tracks. Section 768.28 applies to the state and to its agencies and subdivisions, including counties, municipalities and school districts.

  4. 4

    Claims against a state agency go to two places: the agency and the Department of Financial Services, Division of Risk Management. Only claims against a municipality, county or the Florida Space Authority skip the copy to DFS.

  5. 5

    Section 768.28(6)(c) requires the claimant's date and place of birth and Social Security number, or a federal identification number for a non-individual, plus any adjudicated amounts over $200 owed to the state, or a statement that none exist.

  6. 6

    The agency or DFS has 6 months to make a final disposition, or 90 days for medical malpractice and wrongful death claims. No final disposition in that time counts as a final denial.

  7. 7

    Recovery is capped at $200,000 per person and $300,000 per incident, and punitive damages and pre-judgment interest are excluded. An amount above the cap can be paid only by an act of the Legislature.

Key decisions before you file

Before you file a Notice of Claim in Florida, a few decisions shape the document: which option to choose and what each one means. The Notice of Claim guide walks through them.

Open the Notice of Claim guide

Customize your Notice of Claim Template with DocDraft

Florida Requirements for Notice of Claim

  • Written Claim Within 3 Years

    Fla. Stat. 768.28(6)(a): no action may be brought unless the claim was presented in writing within 3 years after it accrues.

  • Wrongful Death and Contribution Deadlines

    768.28(6)(a): a wrongful death claim must be presented to DFS within 2 years after accrual; a contribution claim within 6 months after the qualifying judgment or discharge.

  • Recipients: Agency and DFS

    Present the claim to the appropriate agency and to the Department of Financial Services, except that claims against a municipality, county or the Florida Space Authority need not go to DFS.

  • Claimant Identification

    768.28(6)(c): give the claimant's date and place of birth and Social Security number, or a federal identification number if the claimant is not an individual.

  • Adjudicated Amounts Owed to the State

    768.28(6)(c): list the case style, tribunal, nature and amount of any adjudicated penalties, fines, fees, restitution or judgments over $200 owed to the state, or state that none exist.

  • Deemed Denial

    768.28(6)(d): no final disposition within 6 months after filing, or 90 days for medical malpractice and wrongful death claims, is deemed a final denial.

  • Suit Within 4 Years

    768.28(14): the action must be commenced within 4 years after the claim accrues; medical malpractice and wrongful death follow s. 95.11(5).

  • Damages Cap

    768.28(5)(a): $200,000 per person and $300,000 per incident or occurrence; no punitive damages or pre-judgment interest; excess only by act of the Legislature.

  • Facts of the Incident

    State the date, time and place, what happened, the agency or employee involved, and the injuries or damage, and keep a record of the date and method of delivery.

Frequently Asked Questions