Arizona Mechanics Lien
File an Arizona mechanics lien to secure payment for construction work. Serve the 20-day preliminary notice, record within 120 days of completion, and enforce.
Introduction
An Arizona mechanics lien is a legal claim recorded against real property by a contractor, subcontractor, or supplier who improved the property and was not paid. Once recorded, the lien attaches to the property, clouds the title, and can be enforced by a court-ordered sale. That security is what gives the lien its leverage, and Arizona provides it under Revised Statutes Title 33, Chapter 7. Arizona is strict about the preliminary notice: nearly every claimant, including the general contractor, must serve a 20-day preliminary notice within 20 days after first furnishing labor or materials to the jobsite. You then record the lien within 120 days after the project is completed, or within 60 days after a notice of completion is recorded, and you must sue to foreclose within six months after recording. DocDraft prepares an Arizona mechanics lien and its notices from your project details, and attorney review is available before you record.
Key Things to Know
- 1
An Arizona mechanics lien secures payment against the improved property. Contractors, subcontractors, material suppliers, equipment lessors, and design professionals who furnished work to the jobsite and were not paid can claim one under Revised Statutes sections 33-981 to 33-1008.
- 2
Arizona requires a 20-day preliminary notice from nearly every claimant, including the general contractor. Under section 33-992.01 it must be served within 20 days after you first furnish labor or materials to the jobsite; only a worker paid wages for labor is excepted.
- 3
Record the lien within 120 days after the building, structure, or improvement is completed. If the owner records a notice of completion, that window shortens to 60 days after recordation, under section 33-993.
- 4
Recording is not the last step. Section 33-998 says the lien does not continue for more than six months after it is recorded unless you bring an action to foreclose it within that period.
- 5
Arizona reads these rules strictly. Missing the 20-day preliminary notice, the 120-day recording window, or the six-month deadline to sue generally forfeits the lien, though a separate contract claim for the debt may survive.
- 6
The preliminary notice follows prescribed language. Section 33-992.01 sets the form and content of the 20-day notice, and the recorded lien must state the amount claimed, the owner, the hiring party, and a description of the property and work.
- 7
Owner-occupied homes get special protection. Under section 33-1002 no lien attaches to the dwelling of someone who became an owner-occupant before the work, except for a claimant who signed a written contract directly with that owner-occupant.
Key decisions before you file
Before you file a Mechanics Lien in Arizona, a few decisions shape the document: which option to choose and what each one means. The Mechanics Lien guide walks through them.
Open the Mechanics Lien guideCustomize your Mechanics Lien Template with DocDraft
Arizona Requirements for Mechanics Lien
File the Arizona mechanics lien in the correct office, a county recorder or court as Arizona requires, within the state's deadline after you last furnish labor or materials. Arizona applies the deadline strictly, so filing late or in the wrong office can void the lien.
Frequently Asked Questions
A mechanics lien in Arizona is a claim an unpaid contractor, subcontractor, or supplier records against the property they improved. It attaches to the real estate and clouds the title, so the owner cannot easily sell or refinance, and it can be foreclosed through a court-ordered sale. Arizona's lien law sits in Revised Statutes Title 33, Chapter 7, sections 33-981 to 33-1008.
Contractors, subcontractors, material suppliers, equipment lessors, and design professionals such as architects and engineers who furnished labor or materials to improve the property and were not paid can file. Almost all of them, including the general contractor, must first serve the 20-day preliminary notice; only a person performing actual labor for wages is excused from it.
You must record the lien within 120 days after the building, structure, or improvement is completed, under section 33-993. If the owner records a notice of completion, the deadline moves up to 60 days after that notice is recorded. The lien is recorded with the county recorder where the property is located.
Yes, and Arizona is unusually demanding here. Under section 33-992.01 nearly every claimant, the general contractor included, must serve a 20-day preliminary notice within 20 days of first furnishing labor or materials to the jobsite. Only a worker paid wages for labor is exempt. Serving late can limit the lien to work furnished within 20 days before the notice.
You have six months from the recording date to file a foreclosure action, under section 33-998. If you do not sue within that window, the lien no longer continues and cannot be enforced against the property. Recording the lien does not extend this deadline, so treat the six-month clock as running from the day you record.
Missing the 20-day notice, the 120-day recording deadline, or the six-month deadline to sue usually means losing the lien, because Arizona applies these steps strictly. You may still sue the party who hired you for breach of contract to recover the money, but you give up the security a lien places on the property.
Arizona shields owner-occupied homes. Under section 33-1002 a person who became the owner-occupant of a dwelling before the work began is protected: no lien attaches to that home unless the claimant had a written contract directly with the owner-occupant. Subcontractors and suppliers on such a home usually cannot lien it and must look to the contractor for payment.
When the debt is paid, the claimant should record a lien release so the title is clear. A lien also expires on its own if no foreclosure action is filed within six months of recording. An owner who believes a lien is invalid can challenge it in court to have it removed and the title cleared.