A preliminary notice is the early written notice a contractor, subcontractor or supplier serves at the start of a construction job so that a mechanics lien stays available later. What it is called, who receives it and how many days you have are set by each state.

Find out where you stand — what state are you in?

DocDraft provides document preparation, not legal advice.

Introduction

A preliminary notice is a written notice that a contractor, subcontractor, equipment lessor or material supplier serves near the start of a construction job, telling the people who control the money that it is on the project and expects to be paid. It is not a demand for payment and it is not a lien. It is the step that keeps the lien available, and in most states a claimant who skips it cannot record a lien at all later, no matter how good the underlying debt is. That is the whole reason this document exists and the reason the deadline matters more than the wording. The clock usually starts from an event rather than from an invoice: the day you first furnished labor or materials to the site, the day the job commenced, or the day the owner recorded a notice of commencement. A few states work the other way around and set no deadline at all, letting you serve whenever you like and then protecting only the work you supplied in a fixed window before the day you served, so that serving later shrinks the claim instead of destroying it. Miss the window and some states bar the lien outright, while others let you serve late and then shrink the claim to the work done in the days just before service. Four things about this notice are set by your own state rather than by any national rule, and they are why the state pages exist. The first is what the document is even called, because the same instrument is a preliminary notice in one state, a pre-lien notice in another, a notice to owner in a third and a notice of furnishing in a fourth. The second is the deadline and the event that starts it. The third is who has to receive a copy, which can be the owner alone or the owner plus the general contractor plus the construction lender. The fourth is the service method, because several states accept nothing short of certified or registered mail with a receipt you keep. Select your state to see its name for this notice, its deadline, its recipient list and its service rule. DocDraft builds your preliminary notice from your facts, with attorney review available before you serve it.

Key Things to Know

  1. 1

    A preliminary notice is an early written notice served at the start of a construction job that preserves the server's right to record a mechanics lien later. It is not itself a lien, and it does not demand payment or create a debt.

  2. 2

    In most states serving it on time is a precondition to the lien, not a courtesy. A claimant who never served the notice usually cannot record a valid lien afterward, even where the money is plainly owed.

  3. 3

    The timing runs off an event on the job, not off an unpaid invoice. In most states that event starts a countdown: the day you first furnished labor or materials, the day the project commenced, or the day the owner recorded a notice of commencement. In a minority there is no countdown to miss, and the notice instead reaches backward to cover only a set period before the day you served it.

  4. 4

    The document goes by different names in different states. Preliminary notice, pre-lien notice, notice to owner and notice of furnishing are all the same instrument performing the same job, so search using your own state's term.

  5. 5

    Who must serve it is a dividing line worth checking first. A subcontractor or supplier with no contract with the owner almost always has to serve one, while a general contractor who signed directly with the owner is often excused or has a lighter obligation.

  6. 6

    States split into two camps on a missed deadline, and the split decides how much a late notice is still worth. One camp bars the lien outright. The other allows late service and then shrinks the claim to the work done shortly before service.

  7. 7

    Public projects usually run on a different track. Public property generally cannot be liened, so the remedy is a claim on the payment bond, and the early-notice step that protects a bond claim can have its own deadline and its own recipients.

Key Decisions

Your Role

The Project

Service

Preliminary Notice Requirements

  • Your Name, Address and Role on the Project

    The claimant's legal name and mailing address, with the relationship to the job stated plainly: subcontractor, sub-subcontractor, material supplier, equipment lessor or design professional. Your role is what determines whether your state requires a notice from you at all.

  • Who Hired You, and the Date of That Contract