Montana Notice of the Right to Claim a Lien
Montana section 71-3-531 requires a notice of the right to claim a lien to the contracting owner within 20 days of first furnishing, by certified mail, with a copy filed at the county. Attorney review available.
Find out where you stand in Montana
What is your role on the construction project?
DocDraft provides document preparation, not legal advice.
Introduction
The date your services or materials are first furnished to the contracting owner is the only event Montana counts from, and it opens either a 20 day window or a 45 day one. Section 71-3-531(3) sets the ordinary period at 20 days after that date. Subsection (4) stretches it to 45 days where the owner is paying from funds provided by a regulated lender and secured against the property for the purpose of paying for that particular improvement, but expressly not on a contract for an owner-occupied residence. Either way a late notice is not fatal in Montana: the lien becomes enforceable only for the services or materials furnished in the 20 days, or 45 days, before the date the notice was given, so every day of delay costs you a day of claim. Before you calendar anything, check whether you owe a notice at all, because Montana has carved this instrument down to small residential work. Section 71-3-531(1) excuses an original contractor who furnishes directly to the owner at the owner's request, a wage earner or laborer, anyone furnishing under a contract relating to a dwelling for five or more families, and anyone furnishing under a contract relating to an improvement that is partly or wholly commercial in character. Commercial jobs and apartment buildings are therefore outside it. If you are inside it, Montana then asks for two steps rather than one: give the notice to the contracting owner by certified mail or personal delivery, and file a copy with the county clerk and recorder within 5 business days. DocDraft builds the Montana notice in the form section 71-3-532 prescribes, with attorney review available as an option.
Key Things to Know
- 1
Section 71-3-532 makes the document announce its own nature in capital letters: THIS IS NOT A LIEN, it is a notice sent to you for your protection in compliance with the construction lien laws of the state of Montana. It warns the contracting owner that if the sender is not paid, a lien may be filed against the property.
- 2
The clock runs from the date on which your services or materials are first furnished to the contracting owner. The ordinary period is 20 days. It becomes 45 days where the owner pays from funds provided by a regulated lender secured against the property for that improvement, excluding a contract on an owner-occupied residence.
- 3
A late notice shrinks rather than destroys the claim. The lien is then enforceable only for the services or materials furnished within the 20 day period, or the 45 day period on the lender-funded track, before the date on which notice is given.
- 4
Four classes do not have to give it: an original contractor furnishing services or materials directly to the owner at the owner's request, a wage earner or laborer performing personal labor services, a person furnishing under a contract relating to a dwelling for five or more families, and a person furnishing under a contract relating to an improvement that is partly or wholly commercial in character.
- 5
Certified mail or personal delivery, and nothing else. Certified mail is effective on the date the notice is mailed, so the postmark is your compliance date. Personal delivery requires written acknowledgment of receipt obtained from the contracting owner.
- 6
Montana is one of the few states that makes you file the notice as well as serve it. A copy, in the form section 71-3-532 requires, must go to the clerk and recorder of the county where the improved real estate is located no later than 5 business days after the notice is given to the owner.
- 7
The filed copy is effective for 1 year and lapses unless you file a 1-year continuation before it expires, and section 71-3-531(6)(e) bars claiming a construction lien unless an unexpired notice or continuation is on file at the time the lien is filed.
Key decisions before you file
Before you file a Preliminary Notice in Montana, a few decisions shape the document: which option to choose and what each one means. The Preliminary Notice guide walks through them.
Open the Preliminary Notice guideCustomize your Preliminary Notice Template with DocDraft
Montana Requirements for Preliminary Notice
Twenty Days From First Furnishing to the Contracting Owner
Section 71-3-531(3) provides that the notice may not be given later than 20 days after the date on which the services or materials are first furnished to the contracting owner. Date that first furnishing from your own delivery tickets or timesheets, because it is the only event the statute counts from.
Forty Five Days Where a Regulated Lender Funds the Payments
Section 71-3-531(4) extends the period to 45 days from first furnishing where payment is made by or on behalf of the contracting owner from funds provided by a regulated lender and secured by an interest, lien, mortgage or encumbrance for the purpose of paying the particular improvement being liened. The subsection expressly excludes a contract on an owner-occupied residence, so the longer window is not available on an owner's own home.
Commercial and Five-or-More-Family Work Is Outside It
Section 71-3-531(1) does not require the notice from an original contractor who furnishes directly to the owner at the owner's request, from a wage earner or laborer performing personal labor services, from a person furnishing under a contract relating to a dwelling for five or more families, or from a person furnishing under a contract relating to an improvement that is partly or wholly commercial in character.
Certified Mail or Personal Delivery With a Signed Acknowledgment
Section 71-3-531(5) requires the notice to be sent to the contracting owner by certified mail or delivered personally to the owner. Certified mail is effective on the date on which the notice is mailed. Personal delivery requires written acknowledgment of receipt obtained from the contracting owner. A person may not claim a construction lien unless the person has complied with that subsection.
File a Copy With the County Clerk Within 5 Business Days
Section 71-3-531(6)(a) requires a copy of the notice, in the form section 71-3-532 prescribes, to be filed with the clerk and recorder of the county where the improved real estate is located, no later than 5 business days after the notice is given to the contracting owner, signed by the filer or an authorized signer. The clerk and recorder may allow electronic filing with an electronic signature.
The Prescribed WARNING and THIS IS NOT A LIEN Text
Section 71-3-532 requires the date of mailing, the owner's name and address, the name and address of the person filing the notice, a description sufficient to identify the property improved, and the prescribed notice text. That text opens WARNING: READ THIS NOTICE. PROTECT YOURSELF FROM PAYING ANY CONTRACTOR OR SUPPLIER TWICE FOR THE SAME SERVICE, states THIS IS NOT A LIEN, and closes with five ways for the owner to protect itself, including joint checks and obtaining evidence of payment or waiver.
Late Notice Cuts the Claim to a Rolling Lookback
If notice is not given within the 20 day period, a lien is enforceable only for the services or materials furnished within the 20-day period before the date on which notice is given, and the lender-funded track applies the same rule with a 45 day lookback. Section 71-3-531(6)(e) separately bars claiming a construction lien unless an unexpired notice, or an unexpired continuation notice, is on file with the clerk and recorder at the time the lien is filed.
One Year Lapse, Continuations, and the Release Once Paid
The filed copy is effective for 1 year from the date of filing and lapses unless a 1-year continuation is filed before it expires, carrying the original file number, its filing date and the name of the person notified. Section 71-3-538 then requires a release to be filed once the claimant is paid, and within 5 business days of the contracting owner's request. Section 71-3-531(7) and (8) also oblige the owner to put the property details and its own name and address in the construction contract, and oblige the original contractor to supply them to a requesting subcontractor or supplier within 5 business days.