New Hampshire Subcontractor Lien Notice
New Hampshire RSA 447:5 lets a subcontractor notify the owner or the person having charge of the property, and RSA 447:8 then requires an account every 30 days. Attorney review available.
Find out where you stand in New Hampshire
What is your role on the construction project?
DocDraft provides document preparation, not legal advice.
Introduction
Either the owner or the person having charge of the property can receive this notice in New Hampshire, and RSA 447:5 treats the two as alternatives rather than ranking them, so a supplier who cannot pin down the record owner can serve whoever is running the site instead. That is the first of three recipients the chapter contemplates. The second is the same pair again, for the recurring account: RSA 447:8 requires any person who gave notice to furnish the owner, or the person having charge of the property, an account in writing of the labor performed, professional design services provided, or materials furnished during the 30 days, as often as once in 30 days. The third is the bank. Where there is a construction mortgage, RSA 447:12-b, I requires the mortgagor or its agent to post the funding institution's name, address and telephone number in a conspicuous place on the jobsite within 10 business days of executing the mortgage, and RSA 447:12-b, II then requires any person entitled to a lien under RSA 447:2-7 to give that institution written notice, within 15 business days of the posting or of commencing to furnish, whichever is later, including the name and address of the jobsite. The two notices carry very different penalties. The owner notice conditions the lien: RSA 447:5 grants a subcontractor the same lien as a direct claimant only provided the notice is given, and RSA 447:6 permits a later notice but limits the lien to the amount then due or that may thereafter become due to the contractor. Missing the lender notice, by contrast, shall not alone invalidate the lien. DocDraft assembles both from your facts, with attorney review available as an option.
Key Things to Know
- 1
RSA 447 gives this document no trade name. RSA 447:5 is headed Subcontractors and RSA 447:6 is headed Notice, and what the statute requires is a notice in writing to the owner, or to the person having charge of the property, that the claimant shall claim such lien. It is not recorded and it is not a lien.
- 2
The owner notice may go to the owner OR to the person having charge of the property. New Hampshire does not force you to establish the record owner first, and RSA 447:8 uses the same pair for the account that follows.
- 3
RSA 447:5 says the notice comes before performing the labor or furnishing the material. RSA 447:6 then allows it afterward, and the price of waiting is reach: the lien is valid only to the extent of the amount then due or that may thereafter become due to the contractor, agent or subcontractor of the owner.
- 4
The duty falls on a claimant whose contract is with an agent, contractor or subcontractor of the owner. A party who contracted with the owner direct takes its lien under RSA 447:2 to 447:4 without giving this notice.
- 5
There is a floor, and it is a small one. RSA 447:5 reaches a person who performs labor, provides professional design services as defined in RSA 447:2, or furnishes materials to the amount of 15 dollars or more.
- 6
The notice starts a repeating obligation. Under RSA 447:8 you must furnish an account in writing, as often as once in 30 days, of what you performed or furnished during the 30 days, and the owner or person in charge must then retain a sufficient sum of money to pay the claim.
- 7
On a mortgaged job there is a second notice. RSA 447:12-b, II requires written notice to the institution providing the construction funds within 15 business days of the jobsite posting or of commencing to furnish, whichever is later, and failure to give it shall not alone invalidate the lien.
Key decisions before you file
Before you file a Preliminary Notice in New Hampshire, a few decisions shape the document: which option to choose and what each one means. The Preliminary Notice guide walks through them.
Open the Preliminary Notice guideCustomize your Preliminary Notice Template with DocDraft
New Hampshire Requirements for Preliminary Notice
The Owner or Whoever Has Charge of the Property
RSA 447:5 requires notice in writing to the owner or to the person having charge of the property, phrased as alternatives rather than a ranking, so service on the party running the site satisfies it. RSA 447:8 uses the same pair for the recurring account, and RSA 447:7 applies the same structure to railroad work by allowing notice to the proprietors or the person having charge of the railroad.
Before the Work, or Later With a Smaller Claim
RSA 447:5 conditions the subcontractor lien on notice given before performing the labor or furnishing the material. RSA 447:6 then permits the notice afterward, and limits the lien to the extent of the amount then due or that may thereafter become due to the contractor, agent or subcontractor of the owner. Read the two together before deciding when to send.
Only Claimants Hired Below the Owner, Above 15 Dollars
RSA 447:5 reaches a person who performs labor, provides professional design services as defined in RSA 447:2, or furnishes materials to the amount of 15 dollars or more, by virtue of a contract with an agent, contractor or subcontractor of the owner. A claimant in direct contract with the owner takes its lien under RSA 447:2 to 447:4 without giving this notice.
Writing Is the Only Prescribed Formality
RSA 447:5 requires notice in writing, RSA 447:8 an account in writing and RSA 447:12-b, II written notice, and none of those sections names a delivery method. Sections 447:5 to 447:14 prescribe no mail rule, no personal service requirement, no notarization and no proof of service, so keep your own dated delivery record and a copy of everything as sent.
No Prescribed Form, One Required Statement
New Hampshire prints no form and no owner warning paragraph for this notice. RSA 447:5 requires the writing to say that the claimant shall claim such lien. The RSA 447:12-b, II lender notice must state that the person is furnishing services, materials, supplies or other things, and must include the name and address of the jobsite.
The 30 Day Account and the Owner's Retention Duty
RSA 447:8 requires any person giving notice under RSA 447:5 to 447:7 to furnish the owner, or the person having charge of the property, an account in writing of the labor performed, professional design services provided, or materials furnished during the 30 days, as often as once in 30 days. The owner or person in charge must retain a sufficient sum of money to pay the claim and is not liable to the agent, contractor or subcontractor for it unless that party first pays the claimant. RSA 447:6 allows the first account to be given with the notice.
Fifteen Business Days to Notify the Construction Lender
RSA 447:12-b, II requires any person entitled to a lien pursuant to RSA 447:2-7 to give the institution providing the construction funds written notice that it is furnishing services, materials, supplies or other things, within 15 business days of the posting required by paragraph I or of commencing to furnish, whichever is later, including the name and address of the jobsite. Paragraph I requires the mortgagor or its agent to post that institution's name, address and telephone number conspicuously on the jobsite within 10 business days of executing the construction mortgage.
Two Notices, Two Very Different Penalties
The owner notice is a condition on the right: RSA 447:5 grants the lien only provided the notice is given. The lender notice is not, because RSA 447:12-b, II states that failure to provide it shall not alone invalidate the lien created by RSA 447:2-7. RSA 447:14 separately provides that no lien shall be defeated by taking a note, unless the note was taken in discharge of the amount due and of the lien.