New Mexico Notice of Right to Claim a Lien
NMSA 1978 Section 48-2-2.1 requires a written notice of the right to claim a lien, sent to the owner or the original contractor no more than 60 days after you initially furnish work or materials. Attorney review available.
Find out where you stand in New Mexico
What is your role on the construction project?
DocDraft provides document preparation, not legal advice.
Introduction
A yard that delivered to a subcontractor, and a sub-subcontractor nobody at the owner's office has heard of, are the two parties NMSA 1978 Section 48-2-2.1 is pointed at. Subsection A lifts the requirement off almost everyone else: it does not reach a claim on residential property containing four or fewer dwelling units, it does not reach a claim by an original contractor, meaning a contractor that contracts directly with the owner, and it does not reach a claim by a mechanic or materialman who contracts directly with the original contractor. Subsection B then adds a money floor, because it bites only on a claim of more than five thousand dollars. So a framing subcontractor hired by the general has nothing to send, and neither does the lumber yard that sells to the general, while the yard that sells to that framing subcontractor does. New Mexico gives the parties it does reach a short written step with no form attached to it: notice in writing of the claimant's right to claim a lien in the event of nonpayment, sent no more than 60 days after initially furnishing work or materials, by certified mail with return receipt requested, by facsimile with acknowledgment, or by personal delivery. It goes to the owner or reputed owner, or to the original contractor if there is one, and the statute lists those two in the alternative. Subsection D wants three things in it and nothing else. Subsection C gives you a lever worth using first: before an owner or original contractor can defend on lack of notice, it has to show it answered your request for the project details within five days. DocDraft builds your New Mexico notice from your facts, with attorney review available before you send it.
Key Things to Know
- 1
The New Mexico instrument is not called a preliminary notice. Section 48-2-2.1 describes it as notice in writing of the claimant's right to claim a lien in the event of nonpayment, and it is the step that keeps a mechanic's or materialman's claim of more than five thousand dollars alive.
- 2
Three classes are outside the requirement under Subsection A: claims on residential property containing four or fewer dwelling units, claims by an original contractor (a contractor that contracts directly with the owner), and claims by a mechanic or materialman who contracts directly with the original contractor. Work out which tier you are on before anything else.
- 3
The money floor is real. Subsection B reaches only a lien claimed in an amount of more than five thousand dollars, so a smaller New Mexico claim carries no notice duty at all.
- 4
The window is 60 days, and it runs from the day you initially furnished work or materials, or both. Not from your contract date, not from an unpaid invoice, and not from the day the job started.
- 5
Only three delivery methods count: certified mail with return receipt requested, facsimile with acknowledgment, or personal delivery. Ordinary first class mail and email are not on the list, and the method you pick is also the only proof the statute leaves you with.
- 6
Subsection D sets the whole content list: a description of the property or a description sufficiently specific for actual identification, the name, address and phone number of the claimant, and the name and address of the person you contracted with or furnished to. New Mexico prescribes no form and no warning paragraph addressed to the owner.
- 7
Serving late is survivable and costly. Under Subsection E you may elect to send the notice later, and the claim then reaches only the work performed or materials furnished on or after the date 30 days prior to the date you sent it.
Key decisions before you file
Before you file a Preliminary Notice in New Mexico, a few decisions shape the document: which option to choose and what each one means. The Preliminary Notice guide walks through them.
Open the Preliminary Notice guideCustomize your Preliminary Notice Template with DocDraft
New Mexico Requirements for Preliminary Notice
Three Exemptions Under Section 48-2-2.1(A)
Subsections B through D do not apply to claims of liens on residential property containing four or fewer dwelling units, to claims by an original contractor (a contractor that contracts directly with the owner), or to claims by a mechanic or materialman who contracts directly with the original contractor. The duty lands on the tier below that: a subcontractor or supplier engaged by a subcontractor.
The Five Thousand Dollar Floor
Subsection B reaches only a lien of a mechanic or materialman claimed in an amount of more than five thousand dollars. A smaller New Mexico claim carries no notice duty. Attorney review available on the scope questions, since the official NMSA compilation page was unreachable and the text was read from the Legislature's own recitation of the section plus one independent published copy.
Sixty Days From Initially Furnishing
The notice must be given not more than sixty days after initially furnishing work or materials, or both. The trigger is your own first delivery or first day of labor on the project, not the contract date and not an unpaid invoice. Fix that date from the delivery ticket before counting.
Owner or Reputed Owner, or the Original Contractor
Subsection B directs the notice to the owner or reputed owner of the property upon which the improvements are being constructed, or to the original contractor, if any. The two are listed in the alternative. New Mexico names no construction lender and no surety as a recipient of this notice.
Certified Mail, Facsimile With Acknowledgment, or Personal Delivery
Only three methods are permitted: certified mail with return receipt requested, facsimile with acknowledgment, or personal delivery. Ordinary first class mail and email are not among them. Section 48-2-2.1 prescribes no proof of notice declaration, so the receipt, the facsimile acknowledgment or a dated delivery record is the only proof you will have.
The Three Content Items in Subsection D
A description of the property or a description sufficiently specific for actual identification of the property; the name, address and phone number, if any, of the claimant; and the name and address of the person with whom the claimant contracted or to whom the claimant furnished labor or materials, or both. New Mexico prescribes no form, no notarization and no warning paragraph addressed to the owner.
Late Service Reaches Back Only Thirty Days
Subsection E lets a person who owes the notice elect not to give it and give it later, and then limits the claim to work performed or materials furnished on or after the date thirty days prior to the date the notice was given. Subsections C and D still apply to a notice given this way.
The Five Day Information Duty on the Other Side
Before an owner or original contractor may defend on lack of notice, Subsection C requires it to show that on your request it furnished you, not more than five days after the request, the original contractor's name, address and license number, the owner's name and address, a description of the property, and the name and address of any bonding company or other surety providing a payment or performance bond. Send that request in writing and keep the copy.