Texas Notice of Claim for Unpaid Labor or Materials

Texas Property Code Section 53.056 requires a derivative claimant to send a notice of claim for unpaid labor or materials to the owner and the original contractor, by the 15th of the third month after the month of the work. Attorney review available.

Find out where you stand in Texas

What is your role on the construction project?

DocDraft provides document preparation, not legal advice.

Introduction

Derivative claimant is the term Texas uses for the party that owes this notice, and the notice the statute prints is captioned NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIALS. Neither phrase is a preliminary notice, and Chapter 53 never uses that expression, so searching for one in Texas sends people to the wrong document. Section 53.056 is headed DERIVATIVE CLAIMANT: NOTICE TO OWNER AND ORIGINAL CONTRACTOR, and subsection (a) makes the notice a validity condition: a claimant other than an original contractor must give the notice prescribed by Subsections (a-1) and (a-2) for the lien to be valid. The timing is set by calendar month rather than by a count of days. For projects other than residential construction projects, the notice must be sent not later than the 15th day of the third month after the month during which the labor or materials were provided, or during which undelivered specially fabricated materials would normally have been delivered. For residential construction projects it is the 15th day of the second month after that month. Because the trigger is the month the work was provided, an unpaid run of months produces a run of notices. Two recipients, not one: the owner or reputed owner and the original contractor. The 2022 amendment changed the heading from owner or original contractor to owner and original contractor, which is a deliberate narrowing. And the notice does real work beyond preserving the lien, because Section 53.081(b) lets the owner withhold funds immediately on receipt of it. DocDraft builds your Texas notice from your facts, with attorney review available before you send it.

Key Things to Know

  1. 1

    Texas calls the sender a derivative claimant, meaning a claimant other than an original contractor, and Section 53.056(a) makes the notice a condition of the lien's validity rather than a courtesy. An original contractor, being in contract with the owner, gives no notice under this section.

  2. 2

    The deadline is a calendar date, not a day count. For projects other than residential construction projects it is the 15th day of the third month after the month during which the labor or materials were provided, or during which undelivered specially fabricated materials would normally have been delivered.

  3. 3

    For residential construction projects the deadline is the 15th day of the second month after that month. Which track applies turns on the Section 53.001 definitions of residential construction project and residential construction contract, which are corroborated from a published copy rather than read off the state's own site, since the Texas statutes site serves no retrievable text. Attorney review is available on that point.

  4. 4

    Two recipients: the owner or reputed owner AND the original contractor. The 2022 rewrite changed the section heading from NOTICE TO OWNER OR ORIGINAL CONTRACTOR to NOTICE TO OWNER AND ORIGINAL CONTRACTOR, so one copy is no longer enough.

  5. 5

    Section 53.003(b) now says a required notice MUST be delivered one of three ways: in person to the party entitled to the notice or that party's agent, by certified mail, or by any other form of traceable, private delivery or mailing service that can confirm proof of receipt. The 2022 amendment turned may into must and dropped registered mail from the list.

  6. 6

    The notice traps money. Section 53.081(a) lets an owner who receives a Section 53.056 notice withhold from payments to the original contractor an amount necessary to pay the claim, in addition to any reserved funds, and Section 53.081(b) allows that withholding immediately on receipt.

  7. 7

    Dates matter twice over, because Section 37 of the 2021 act limits the whole rewrite to an original contract entered into on or after January 1, 2022. An original contract signed before that is governed by the prior law, which the act continues in effect for that purpose.

Key decisions before you file

Before you file a Preliminary Notice in Texas, a few decisions shape the document: which option to choose and what each one means. The Preliminary Notice guide walks through them.

Open the Preliminary Notice guide

Customize your Preliminary Notice Template with DocDraft

Texas Requirements for Preliminary Notice

  • Only a Derivative Claimant Sends It

    Section 53.056 is headed DERIVATIVE CLAIMANT: NOTICE TO OWNER AND ORIGINAL CONTRACTOR, and subsection (a) applies it to a claimant other than an original contractor, except as provided by Section 53.057. An original contractor, holding the contract with the owner, sends nothing under this section. Subcontractors, sub-subcontractors, material suppliers and equipment suppliers below the original contractor are inside it.

  • The 15th Day of the Third Month After the Month of the Work

    Section 53.056(a-1) requires the notice to be sent, for projects other than residential construction projects, not later than the 15th day of the third month after the month during which the labor or materials were provided, or during which the undelivered specially fabricated materials would normally have been delivered. The trigger is each such month, so an unpaid run of months produces a run of notices with separate dates. Section 53.003(e) extends a period whose last day is a Saturday, Sunday or legal holiday to the next day that is not.

  • Residential Construction Projects Run on the Second Month

    For residential construction projects, Section 53.056(a-1)(2) sets the deadline at the 15th day of the second month after the month during which the labor or materials were provided or the undelivered specially fabricated materials would normally have been delivered. Which track applies turns on the Section 53.001 definitions of residential construction project and residential construction contract, which are corroborated here from a published copy current as of January 2026 rather than read off the Texas statutes site, which serves no retrievable text. Attorney review available on this point.

  • The Owner or Reputed Owner AND the Original Contractor

    Section 53.056(a-1) requires the claimant to send the notice to the owner or reputed owner and the original contractor. The 2021 act changed the section heading from NOTICE TO OWNER OR ORIGINAL CONTRACTOR to NOTICE TO OWNER AND ORIGINAL CONTRACTOR, so notifying one of them is not compliance. The printed form asks separately for the original contractor's name and for the party with whom the claimant contracted if different, which is the prompt that matters on a multi-tier job.

  • Three Mandatory Delivery Routes, and Registered Mail Is No Longer One

    Section 53.003(b) provides that a notice required by the chapter must be delivered in person to the party entitled to the notice or to that party's agent, by certified mail, or by any other form of traceable, private delivery or mailing service that can confirm proof of receipt. The 2021 act turned may into must and removed registered mail. Section 53.003(c) adds that where notice is sent by certified mail, deposit or mailing in the United States mail in the form required constitutes compliance, except where the law requires actual receipt.

  • The Printed Form and Its WARNING Line

    Section 53.056(a-2) requires the notice to be in substantially the statutory form, captioned NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIALS, carrying the line WARNING: This notice is provided to preserve lien rights, and the sentence that the owner's property may be subject to a lien if sufficient funds are not withheld from future payments to the original contractor to cover this debt. The fields are Date, Project description and/or address, Claimant's name, Type of labor or materials provided, Original contractor's name, Party with whom claimant contracted if different from original contractor, Claim amount, the claimant's contact person and the claimant's address. Section 53.056(a-3) allows an invoice or billing statement to be included.

  • The Notice Lets the Owner Withhold Funds Immediately

    Section 53.081(a) lets an owner who receives notice under Section 53.056 or 53.057 withhold from payments to the original contractor an amount necessary to pay the claim, in addition to any reserved funds, and Section 53.081(b) allows that withholding immediately on receipt of a Section 53.056 notice. Section 53.082 requires the owner to retain the funds until the time for filing the lien affidavit has passed or, if one was filed, until the claim is satisfied or released, unless settled, discharged, indemnified against under Subchapter H or I, or held invalid by final judgment. Section 53.084(b) makes the owner liable for money paid to the original contractor after the owner was authorized to withhold.

  • Retainage Has Its Own Notice, and Pre-2022 Contracts Have Their Own Law

    Section 53.057(a) requires a separate notice of claim for unpaid retainage, to the extent that claim is not included wholly or partly in a Section 53.056 notice, and Section 53.057(a-1) sets it at the earlier of the 30th day after the claimant's contract is completed, terminated or abandoned or the 30th day after the original contract is terminated or abandoned, with its own form captioned NOTICE OF CLAIM FOR UNPAID RETAINAGE. Separately, Section 37 of the 2021 act applies the entire rewrite only to an original contract entered into on or after January 1, 2022, continuing prior law in effect for earlier original contracts, and Section 36 repealed the old Sections 53.056(b) to (f), 53.058, 53.252 and 53.253 outright.