Alabama Notice to the Owner or Proprietor
Code of Alabama Section 35-11-210 lets a material supplier notify the owner or proprietor in writing before furnishing any material, and that advance notice is what buys a lien for the full price instead of a lien capped at the unpaid balance due the contractor. Attorney review available.
Find out where you stand in Alabama
What is your role on the construction project?
DocDraft provides document preparation, not legal advice.
Introduction
Notice to the owner or proprietor is the phrase Code of Alabama Section 35-11-210 uses, and in Alabama that one piece of paper decides whether a supplier has a lien for the full price of its material or a lien capped at whatever the owner still owes the contractor. The section gives a materialman supplying a contractor or subcontractor a lien that extends only to the amount of any unpaid balance due the contractor by the owner or proprietor. Then it opens a door. A supplier that notifies the owner or the owner's agent in writing, before furnishing any material, that certain specified material will be furnished at certain specified prices has a lien for the full price as specified in the notice, without regard to whether the claim exceeds the unpaid balance. There is no number of days in the Alabama provision. There is a point in the job: the writing has to be in the owner's hands before the material goes out, which means this is a credit-approval step, not a collections step. Alabama also prints the words. Section 35-11-210 sets out a short form addressed to the owner or proprietor and says that form shall be sufficient. The owner gets a reply, too: if the owner or the agent writes back before the material is used saying it will not be responsible for the price, the full price lien does not follow. Section 35-11-232 widens who counts as the owner, Section 35-11-218 adds a second written notice later for everyone except the original contractor, and Section 35-11-219 puts the original contractor under a duty to hand the owner a list of everyone supplying the job. DocDraft builds your Alabama notice from your facts, with attorney review available before you send it.
Key Things to Know
- 1
Alabama's early notice is the advance writing Section 35-11-210 lets a material supplier give the owner or proprietor, or the owner's agent, before any material is furnished. Nothing is recorded and nothing is filed. Its whole job is to move the supplier from a lien on the unpaid balance due the contractor to a lien for the full price specified in the notice.
- 2
There is no Alabama day count to calculate. Section 35-11-210 says the supplier must notify the owner 'before furnishing any material', so the deadline is the first delivery itself. Send the notice when the order is accepted, not when an invoice ages.
- 3
The notice has to state certain specified material at certain specified prices. That wording is load-bearing, because the lien it buys is for the full price 'as specified in the notice', so the prices you write become the ceiling. Itemize instead of writing an estimate.
- 4
Section 35-11-210 prints its own form, addressed 'To __________, owner or proprietor', and says the notice may be given in that form, which shall be sufficient. The form ends with the sentence that there will become due to the undersigned the price of the material, for the payment of which the undersigned will claim a lien.
- 5
The owner can answer and cut it off. If the owner or proprietor or the agent notifies the supplier in writing, before the material is used, that it will not be responsible for the price, the full price lien does not follow. Read everything that comes back from the owner and keep it.
- 6
Section 35-11-210 requires the notice to be in writing and names no delivery method, no mail class and no proof of service. Alabama does not hand you a return receipt rule to hide behind, so the supplier's own evidence that the writing reached the owner or the agent before material went out is what carries the point.
- 7
Alabama has a second, separate notice. Section 35-11-218 requires every person except the original contractor to give the owner or the agent written notice that a lien is claimed, stating the amount, for what, and from whom it is owing, and then holds any unpaid balance in the owner's hands subject to that lien. Material already noticed in advance under Section 35-11-210 is excepted.
Key decisions before you file
Before you file a Preliminary Notice in Alabama, a few decisions shape the document: which option to choose and what each one means. The Preliminary Notice guide walks through them.
Open the Preliminary Notice guideCustomize your Preliminary Notice Template with DocDraft
Alabama Requirements for Preliminary Notice
Notice to the Owner or Proprietor, or the Owner's Agent
Section 35-11-210 names one recipient class: the owner or proprietor, or the owner's agent. Alabama requires no statutory copy to the general contractor and none to a construction lender. Section 35-11-232 embraces within owner or proprietor every person, including cestuis que trust, for whose use, benefit or enjoyment the building or improvement is made.
Before Furnishing Any Material, With No Day Count
Section 35-11-210 requires the supplier to notify the owner in writing before furnishing any material. Alabama states no number of days, so there is no window to count: the first delivery is the deadline. Send the notice when the order is taken.
Full Price Lien Instead of the Unpaid Balance
Without the advance notice, a person furnishing material to the contractor has a lien that extends only to the amount of any unpaid balance due the contractor by the owner or proprietor. With it, the supplier has a lien for the full price as specified in the notice, without regard to whether the claim exceeds that unpaid balance (Section 35-11-210).
Certain Specified Material at Certain Specified Prices
Section 35-11-210 conditions the full price lien on a notice that the supplier will furnish certain specified material at certain specified prices, and then measures the lien by the full price as specified in the notice. Itemize the material and state the prices, because what is written sets the ceiling.
The Statutory Form Section 35-11-210 Says Is Sufficient
The section prints a form addressed to the owner or proprietor, stating that the undersigned is about to furnish the named contractor or subcontractor certain material for the construction, or for the repairing, altering, or beautifying of a building or improvement on the described property, and that there will become due to the undersigned the price of the material, for the payment of which the undersigned will claim a lien. The statute says the notice may be given in that form, which shall be sufficient.
In Writing, With No Prescribed Delivery Method
Section 35-11-210 requires the notice to be in writing and prescribes no mail class, no personal delivery requirement, no electronic option and no proof of service. Nothing is filed with any Alabama office. Because the full price lien turns on the owner having been notified before material was furnished, use a method that leaves a dated receipt and keep it.
The Owner's Written Refusal of Responsibility
Section 35-11-210 lets the owner or proprietor or the agent notify the supplier in writing, before the material is used, that it will not be responsible for the price, and the full price lien then does not follow. Date-stamp and keep anything the owner sends back, and check it against the date the material went into the job.
The Separate Section 35-11-218 Notice, and the Contractor's List
Section 35-11-218 requires every person except the original contractor to give the owner or the agent written notice that a lien is claimed, stating the amount, for what, and from whom it is owing, after which any unpaid balance in the owner's hands is held subject to that lien. Material already noticed in advance under Section 35-11-210 is excepted. Section 35-11-219 separately obliges the original contractor to furnish the owner a complete list of all materialmen, laborers and employees with the terms and price when required, and forfeits the contractor's own lien right for refusing.